If you have driven by this week, you have probably seen sparks flying. There has been a lot of welding going on - there is a LOT of steel in the building because of the weight of the books. This week has been a busy week for the workers, but you can't see a lot from the street. Several library staff and project team members were treated to a tour on Friday, August 8th. It is exciting to see all of the activity. Some cool pictures to show you - most of the steel flooring for the second floor has been installed and now the rebar supports are being put in before the concrete pour. The rebar sticking up looks somewhat torturous, like a bed of nails! There is also a cool view of the elevator shaft with the sky above, and the impending storm.