Thursday, December 11, 2008

Oh the Weather outside is frightful...



Brrrrrr! It's 37 degrees right now, and falling fast, but we've got some major movement on the building this week!


The windows are (slowly) arriving. The five windows in the back of the building are in, as well as a window on the Goethals side of the building. The rest of them are on their way, and installation will continue as the pieces get here.

The remaining openings will be covered in plastic, and Chervenell will begin to heat the inside of the building. That means that they are able to start taping drywall pretty soon.


The plumbing rough-in is nearly completed, and the framing is almost finished as well.

If you've driven down Goethals, you'll notice that the curbing of the parking lot is almost finished. The plan is to do the first pour by the end of this week for the parking lot, and have it completely finished before the end of the year.

In the building itself, the first of the two elevators (called, imaginatively enough, elevator #1) is finished.


Over here in the temp building, there is a children's program this afternoon, and on December 19th beginning at noon, we will be having our annual holiday movie marathon. Because the space is limited here, we are partnering with the Community Center to show the movies. For more information, please call the Library at 509-942-7454.

Theresa